Planned Projects

2025 ROAD CONSTRUCTION PROJECTS
Projects are in progress or planned to begin in 2025
ASPHALT OVERLAYS WILL BEGIN ON TUESDAY APRIL 15TH
2025 Asphalt Overlay Roads in no particular order:
- Birkhead Rd -- In Progress
- Bunker Hill Rd -- Completed
- Camp Charren Rd
- Fairview Church Rd
- Meier Rd (South of Brevator Rd) -- Completed
- Old Hwy E -- Completed
- Silex Elevator Rd -- Completed
- S. Ethlyn Rd
- Quarry Rd
- White Wildlife Rd -- Completed April 15th.
- Himmel Rd -- Late May Start
- Linns Mill Rd
- Old Hwy 79
- Gravens Rd -- Planned to start the week of May 19-22
2025 New Asphalt Roads:
- Quarry Rd (2 miles)
- Birkhead Rd (0.1 miles) -- completed
- Straube Rd (1600 feet) cost share project
2025 Asphalt Roads to be crack sealed and/or fog sealed:
- Roads are currently being rated to determine list.
2025 Road Construction and large projects
- S. Ridge Rd — replace narrow box culverts and other culverts
- Kelch Rd -- replace narrow box culverts and other culverts
- Beck Rd -- replace narrow box culverts and other culverts
- Louisville Rd -- replace large diameter culverts
- Blackmore Rd -- roadway improvements along gravel road section -- Summer/Fall 2025
- Zoar Church Rd — Low Water Crossing replacement with Box Culvert————————–Late Summer/Early Fall Construction Date
- Straube Rd -- roadway improvements -- In Progress
- Patton Rd -- safety and roadway improvements -- In Progress
2025 ROAD CONSTRUCTION PROJECTS
Projects are in progress or planned to begin in 2025
ASPHALT OVERLAYS WILL BEGIN ON TUESDAY APRIL 15TH
2025 Asphalt Overlay Roads in no particular order:
- Birkhead Rd -- In Progress
- Bunker Hill Rd -- Completed
- Camp Charren Rd
- Fairview Church Rd
- Meier Rd (South of Brevator Rd) -- Completed
- Old Hwy E -- Completed
- Silex Elevator Rd -- Completed
- S. Ethlyn Rd
- Quarry Rd
- White Wildlife Rd -- Completed April 15th.
- Himmel Rd -- Late May Start
- Linns Mill Rd
- Old Hwy 79
- Gravens Rd -- Planned to start the week of May 19-22
2025 New Asphalt Roads:
- Quarry Rd (2 miles)
- Birkhead Rd (0.1 miles) -- completed
- Straube Rd (1600 feet) cost share project
2025 Asphalt Roads to be crack sealed and/or fog sealed:
- Roads are currently being rated to determine list.
2025 Road Construction and large projects
- S. Ridge Rd — replace narrow box culverts and other culverts
- Kelch Rd -- replace narrow box culverts and other culverts
- Beck Rd -- replace narrow box culverts and other culverts
- Louisville Rd -- replace large diameter culverts
- Blackmore Rd -- roadway improvements along gravel road section -- Summer/Fall 2025
- Zoar Church Rd — Low Water Crossing replacement with Box Culvert————————–Late Summer/Early Fall Construction Date
- Straube Rd -- roadway improvements -- In Progress
- Patton Rd -- safety and roadway improvements -- In Progress